Kramat Lontar Gang 10 Drainage Work 60 Percent Complete

Drainage normalization project in residential area of Jakan Kramat Lontar Gang 10, RW 01, Paseban Urban Village, Senen, has reached over 60 percent completion. The project, carried out by Central Jakarta Water Resources (SDA) Sub-agency since July, is progressing steadily.

"We aim to complete the work by October 15,"

Damaged Retaining Wall in Kelapa Gading Timur Being Repaired

Senen Sub-district SDA Unit Head, Zulfahmi, mentioned that the 270-meter-long drainage is being normalized by installing 40x60 centimeters U-ditch concrete channels.

"So far, we've completed 180 meters, or approximately 66.6 percent of the total length," said Zulfahmi on Thursday (10/2).

According to him, the project was proposed by residents through Rembuk RW and included in the 2024 Musrenbang.

"We aim to complete the work by October 15," he added.

The project received positive feedback from Bambang (43), a local resident, who said the old drainage was too narrow to handle heavy rainfall.

"Hopefully, the work finishes soon so we won't have to worry about flooding during peak rainy season," he expressed.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1398 personFakhrizal Fakhri
  2. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye991 personAldi Geri Lumban Tobing
  3. CNY 2577 Kongzili: Matakin Calls for Justice and Solidarity

    access_time22-02-2026 remove_red_eye866 personAldi Geri Lumban Tobing
  4. Jalan RS Fatmawati Widening Supports Transit-Oriented Development

    access_time19-02-2026 remove_red_eye726 personTiyo Surya Sakti
  5. One-Year Reflection: Pram-Rano Outline Performance Achievements

    access_time21-02-2026 remove_red_eye649 personDessy Suciati